Topic guides
Quality management for AAA: ISQM 1, ISQM 2 and ISA 220
A quality management question usually hands you a file note full of problems: an engagement partner who never reviewed the going concern work, a trainee on a complex group, a deadline moved forward by two weeks. Scoring means naming the standard each problem breaches, explaining why it matters to this audit, and saying what the firm should do. The line I come back to most on this topic is one every auditor learns early: not documented, not performed.
Two levels: the firm and the engagement
| Standard | Level | What it requires |
|---|---|---|
| ISQM 1 | The firm | A system of quality management built on quality objectives, the risks to them, and responses to those risks |
| ISQM 2 | The firm, for chosen engagements | Engagement quality reviews: who can do them and what they cover |
| ISA 220 (Revised) | The single audit | The engagement partner's responsibility for managing and achieving quality on that audit |
Keep the levels apart in your answer. A trainee left unsupervised on one audit is an ISA 220 problem. A firm that never checks whether its partners supervise is an ISQM 1 problem.
ISQM 1: the eight components
| Component | What a weakness looks like |
|---|---|
| The firm's risk assessment process | Quality objectives set once and never revisited |
| Governance and leadership | Partner bonuses driven by fee income alone |
| Relevant ethical requirements | No annual independence confirmations collected |
| Acceptance and continuance | A client kept on despite unpaid fees and a breakdown of trust |
| Engagement performance | No review of the riskiest areas before signing |
| Resources | Staff without industry experience put on a specialist audit |
| Information and communication | Inspection findings never shared with audit teams |
| Monitoring and remediation | Deficiencies found, root causes never identified |
ISQM 1 asks for responses designed for the firm's own risks. Writing "the firm should improve its controls" earns little. "The firm should require a second partner review of going concern work on every audit where a covenant is tested within 12 months" earns credit.
ISQM 2: engagement quality reviews
ISQM 1 requires an engagement quality review for:
- audits of listed (publicly traded) entities
- audits where law or regulation requires one
- any engagement where the firm decides a review is the right response to a quality risk
The reviewer must be competent, must be objective, and must not have been the engagement partner on that audit in the previous two years. The review must be finished before the auditor's report is dated.
ISA 220 (Revised): the engagement partner
The engagement partner is responsible for quality on the audit and must be involved enough to show it. The standard expects:
- direction and supervision that suit the team's experience
- timely review of the work, especially significant judgements
- a stand-back before the report is signed: is the partner satisfied that their involvement was sufficient and appropriate throughout the audit?
When a scenario shows a partner who signed without reviewing the riskiest work, say that the partner cannot show sufficient involvement, and say what has to happen before the report is issued.
Reviews and root causes
| Review | When | Purpose |
|---|---|---|
| Hot review | Before the report is signed | Catch problems on this audit |
| Cold review | After the report is signed | Find patterns across audits |
| Root cause analysis | After a deficiency is found | Fix the cause rather than the symptom |
Technology and quality
| Approach | Quality risk | Response |
|---|---|---|
| Data analytics | The extract may be incomplete | Reconcile record counts and totals to the general ledger before relying on any test |
| Remote auditing | Physical existence is harder to evidence | Attend counts in person for material inventory, or use live video with the auditor directing the camera |
| Automated tools | Teams over-rely on output | Have scripts reviewed by someone who did not write them, and document how each exception was cleared |
Analytics supports substantive testing. It replaces none of it unless the evidence it produces is sufficient on its own.
Before you submit
- Each problem is tied to the right standard and the right level.
- Each problem says why it matters to this audit.
- Each recommendation is specific to the firm in the scenario.
The framework for audit quality
The IAASB's framework looks at audit quality from five angles. A good answer to a quality question often touches more than one.
| Element | What it covers | A weakness in a scenario |
|---|---|---|
| Inputs | Values, ethics, knowledge, experience and time | A team without industry experience |
| Process | The methodology and how the work is done | No review of significant judgements |
| Outputs | The auditor's report and communications | A report signed before the work was finished |
| Interactions | Contact with management and those charged with governance | Findings never discussed with the audit committee |
| Context | Law, regulation, governance and the wider environment | A deadline cut without the scope changing |
Common mistakes on quality questions
- Writing ISQC 1, which ISQM 1 replaced.
- Treating every problem as a firm-level failure, when it may be one partner on one audit.
- Recommending "more training" or "a bigger sample" without tying it to the specific failure in the scenario.
- Forgetting documentation. Under ISA 230, work that is not documented is treated as not performed.
Test yourself
1. Which standard governs quality on a single audit engagement?ISQM 1 · ISQM 2 · ISA 220 (Revised) · ISA 230Show answer
Answer: ISA 220 (Revised). ISQM 1 sets the firm's system; ISQM 2 covers engagement quality reviews.
2. How long must a former engagement partner wait before acting as engagement quality reviewer on the same audit?No wait · One year · Two years · Five yearsShow answer
Answer: Two years.
3. When must the engagement quality review be finished?Before the auditor's report is dated · Within a month of signing · At the next cold review · Before the planning meetingShow answer
Answer: Before the auditor's report is dated.
4. Which ISQM 1 component covers a firm where partner bonuses depend on fee income alone?Resources · Governance and leadership · Monitoring and remediation · Engagement performanceShow answer
Answer: Governance and leadership. Rewarding fees over quality sets the wrong tone.
5. Which review takes place after the auditor's report is signed, to find patterns across audits?Hot review · Cold review · Engagement quality review · Stand-backShow answer
Answer: Cold review.
Current against the December 2026 examinable documents list, checked 20 November 2026.